A good tender for electrical and ELV works defines the scope, drawings, specifications, bill of quantities, approved materials, testing and handover requirements in enough detail that every bidder prices the same work. Most disputes and variations come from gaps in these documents, not from construction itself.

1. Scope and interfaces

  • A written scope of work listing every system included and excluded.
  • An interface matrix with civil, mechanical, fire-fighting, lifts and IT packages: who supplies, installs, connects and tests what.
  • Site constraints: working hours, occupied areas, access and storage.

2. Drawings and specifications

  • A drawing register with revision numbers for every issued drawing.
  • Single-line diagrams, layouts, riser diagrams and schedules.
  • Technical specifications for each system, referencing the codes that apply, such as the Saudi Building Code.

3. Bill of quantities

  • Measured quantities that match the drawings.
  • Stated measurement rules, for example how cable is measured and what each item includes.
  • Separate items for testing, commissioning, documentation and training.

4. Materials and submittals

  • An approved manufacturers list, or performance criteria for equivalents.
  • Submittal requirements: datasheets, samples, shop drawings and calculations.
  • Compatibility rules, for example one cabling system from end to end.

5. Testing and commissioning

  • Test procedures and acceptance criteria for each system.
  • Factory and site acceptance tests where relevant.
  • Witnessing by the owner or consultant, and authority inspections such as Civil Defense for fire alarm.

6. Handover

  • As-built drawings and test reports.
  • Operation and maintenance manuals.
  • Training sessions for the operator's staff.
  • Warranty period, defects liability period and recommended spare parts.
  • Software licences, passwords and configuration backups for every system.

Evaluating the bids

Compare each offer line by line against the BOQ, list exclusions and deviations, check proposed makes against the approved list, and clarify gaps before award. The lowest total is not always the lowest cost once missing items are priced in.

Frequently asked questions

What is a BOQ?

A bill of quantities lists every item of work with its measured quantity, so bidders price the same scope and payments can be measured.

What is an interface matrix?

A table that assigns responsibility for each connection between packages, for example who supplies and connects the fire alarm interface to the lifts.

Why do tenders lead to variations?

Usually because of missing scope, drawings that do not match the BOQ, or unclear interfaces between packages.

Related services

Consulting & studiesElectrical designProject management & supervision

Have a project in mind?

Tell us what you need. We will come back with a scope, a timeline and next steps.

Start a project